Strong progress continues at Hale’s Punchbowl multi-level warehouse project in NSW.
The team have completed the flood conveyance slab works for the western carpark. The structural steel for the suspended slab has been completed with kingflor installed.
Bulk earthworks are underway at tenancies 01,02,03,04,07 and 08 while office and warehouse structural steel is being erected at tenancies 05,06,11 and 12.
Once complete, the 37,000m² 12-unit facility will include an undercover loading area, dedicated corporate offices, undercover parking and EV charging.
Well done to our NSW team and our valued client Hale for the fantastic efforts onsite!